KnowledgeECONOMICS
CONTACT US
Hunan Perfect Industry Co.,Ltd
Contact: Manager Hu, Manager Yi
Hotline:008618507312158
Cell phone:008613974960765
Address:Xiangyin County Industrial Park, Yueyang City, Hunan Province, China
Current location: HOME »Knowledge »vertical turbine pump
Uncrating and Cleaning of the vertical turbine pump
If the unit appears undamaged proceed to uncrate following the instructions given below:
DEFLECTION OF the vertical turbine pump
To prevent deflection of the vertical turbine pump components, take appropriate precaution to prevent the
weight of the vertical turbine pump from resting on the suction bell or case, when lifting to vertical position.
Refer to Figure 4-1.
• Clean all the parts of any dirt, packing material or other foreign matter.
• Flush the vertical turbine pump inside and outside with clean water or a fluid compatible with pumpage. If the vertical turbine pump is for potable water, a lightly chlorinated flush may be recommended.
• Clean all machined surfaces as these are coated with a rust preventative before shipment, which must be removed.
• Remove any rust spots found on the machined surfaces with a fine emery cloth.
• Clean all threaded connections and any accessory equipment.
Parts and accessories may be placed inside shipping containers or attached to skids in individual packages. Inspect all containers, crates and skids for attached parts before discarding.
When lifting an assembled pump, it must be supported at minimally two locations. When lifting to the vertical position, use the discharge head lifting lug locations to lift the vertical turbine pump assembly (refer to Figure 4-1 ). For pump units over 40 ft in length, the vertical turbine pump shall be assembled during installation vertically in place over the mounting location.
Installation Equipment and Tools
Do not attempt installation without proper equipment. The following list covers the major equipment and tools.
required for installation:
1. Mobile crane capable of hoisting and lowering the weight of the vertical turbine pump or motor (refer to Figure 4-1 ).
2. Cable sling for attaching to the vertical turbine pump and motor lifting eyes (refer to Figure 4-1 ).
3. Ordinary hand tools such as end wrenches, socket set, screw drivers, allen wrenches, etc.
4. Wire brush, scraper and fine emery cloth.
5. Thread sealing compound, light machinery oil and a thread lubricant.
6. Tank or barrel flange gasket and flange bolts & nuts (Can Pumps).